A34 Progress Report April 12, 2024

-Milford 13th Street will be closed to non-local traffic starting April 15th. Barricades will be placed along Highway 71, the East edge of the intersection of 213th Ave and 13th Street, and all side streets that intersect 13th Street. There will be openings at these barricades, to allow access for residents on 13th Street/Airport Drive only. 

 

-Milling and pavement removal operations will begin April 16th. Residents along 13th Street will be able to access their driveways during this time, but shall use caution around the construction equipment. 

 

-Temporary water will be installed following the milling operations. Expect construction personnel conducting work in front of your residence. 

 

-Please place garbage/recycling cans at the end of your driveways on the appropriate days for construction personnel to collect. If you would like your same garbage can back, please write your home address on the can. 

 

-Emergency personnel have been contacted and will be updated weekly, to ensure a quick response in the case of an emergency. 

 

-Residents with a mailbox mounted on the house will have no change in mail delivery. Residents with a mailbox along the road, will need to collect their mail at the two locations I have listed below.  

 

Airport Drive Temp Mailboxes will be located in front of 36 Airport Drive for the following homes: 

-4 Airport Drive 

-6 Airport Drive 

-8 Airport Drive 

-39 Airport Drive 

-40 Airport Drive 

-41 Airport Drive 

 

13th Street Temp Mailboxes will be located along H Avenue on the East side of Accura Healthcare for the following homes:

-1310 13th Street

-1312 13th Street

-1400 13th Street

-1402 13th Street

-1404 13th Street

-1406 13th Street

-1408 13th Street

-1410 13th Street

-1412 13th Street

-1600 13th Street

-1804 13th Street

-1806 13th Street

-1808 13th Street

-1902 13th Street

-1903 13th Street

-2132 220th Street

 

-Updated progress reports will be posted weekly, to notify residents where the majority of the construction work will take place for the following week. 

-If you would like emailed progress reports, please request those from Tyler Lynn, tlynn@beck-engineering.net