A34 Progress Report July 11, 2024

The contractor will be continuing east from N Avenue towards Highway 71, installing water and sanitary sewer mains. At times, there will be work being done west of N Avenue as they will be tying in new sanitary sewer and water services. As mentioned before, the contractor will do their best to backfill open trenches at the end of each day, but anticipate lack of driveway access at times. The contractor anticipates reaching Highway 71 with both water and sanitary sewer mains within the next week/week and a half(weather dependent). Once they have reached the highway, they will jump over to Westview Drive and head west towards 213th Avenue/Airport Drive. The closure of 213th Ave/13th Street will be determined within the next few weeks(weather dependent).

The contractor will also be heading east of H Avenue with storm sewer. The contractor will do their best to backfill open trenches at the end of each day, but anticipate lack of driveway access at times.

Weather depending, the rock will soon be placed from H Avenue to Clover Lane. The rock cannot be placed until things start to dry out on the site. Once this is completed, the access from Westview Drive to Airport Drive will be closed, to allow work to continue west. You will be notified a few days in advance of the access switch.

Please feel free to reach out if you have any questions/comments and I will address them as quickly as I can.

 

Thanks,

Tyler Lynn, Sr. Engineering Technician 

Beck Engineering, Inc. 