A34 Progress Report June 19, 2024

The contractor will be continuing east from M Avenue towards Highway 71, installing water main and sanitary sewer main. At times, there will be work being done west of M Avenue as they will be tying in new sanitary sewer and water services. As mentioned before, the contractor will do their best to backfill open trenches at the end of each day, but anticipate lack of driveway access at times.

A third crew has begun work installing storm sewer within the intersection of H Avenue. Once storm sewer is installed past Clover Lane and rock is added to the road bed, the temporary access will be switched back (Clover to H Ave). I will provide a date of this switch once crews are closer to that point.

If your trash or recycling was not collected on the scheduled day, please continue to leave it out the following day and crews will collect it. If you are concerned with it blowing away due to the never-ending storms, please place it inside and set it back out the following day.

Please feel free to shoot me an email if you have any questions or comments and I will address them as soon as I can.

Thanks,

Tyler Lynn, Sr. Engineering Technician 

Beck Engineering, Inc. 