A34 Progress Report June 5, 2024

The contractor will have two crews working east of K Avenue towards Highway 71. One crew will be installing sanitary sewer while the other follows installing water main. The contractor will do their best to backfill open trenches at the end of each day, but anticipate lack of driveway access at times.

A third crew has begun work installing storm sewer within the intersection of H Avenue. Once storm sewer is installed past Clover Lane, the temporary access will be switched back (Clover to H Ave). Beck Engineering will provide a date of this switch once crews are closer to that point.